Contractor of NPP Belene Selected
On October 30, 2006, at its session the NEK Board of Directors,
after having considered the Evaluation report of the Evaluation
Committee, took a decision on the Procedure on awarding a public
procurement order for design, construction and commissioning of
Units 1 and 2 of NPP Belene. The Board of Directors awarded the
procurement to Atomstroyexport with variant À92 for construction of
2x1000 MW light-water reactor units at the site of Belene. The offer
submitted by Skoda Alliance was ranked second.
The offers were evaluated based on the criteria defined in the
documentation for participation in the procedure, current
methodologies for technical and economic evaluation of bid for
nuclear power plants developed by the International Atomic Energy
Agency as well as specialized risk assessment software package.
The main advantages of the selected variant À92 (two B466 reactor
units) are as follows:
a
Significant margins in the safety characteristics and features, such
as secondary containment, 4 train safety channels and extended
capacity of the passive safety elements
a
Lower risk of unforeseen extension of the construction schedule, of
licensing complications, or of early necessity of safety related
improvements
a
Use of newest technologies and longer operational life-time (60
years)
a
VVER reactor of third generation being best recognized in the
European Union.
|